22-25-Central Energy Plant # 3
Project Overview:
Demolition of an existing grounds building to make way for the new Central Energy
Plant #3 and cooling tower. This plant is a facility designed to distribute heating
and cooling capacity to the campus central loop and assist with the heating and cooling
capacity at the new College of Medicine as it comes online in 2026.
Client: University of South Alabama
Estimated Construction Completion Date: January 2026
Construction Contract: $15,571,771.00
SF: 10,975 SF
Primary Use: Provide heating and cooling capacity to buildings on campus.
Design Contract: Burns McDonnell
Construction Contract: Ben M. Radcliff Contractor, Inc.
Target Timeline:
Bid Date: 8/31/23
Start Construction: 11/21/24
Construction Completion Date: 1/14/26